From Forest City lawsuit vs. Skanska:
Skanska failed to meet Milestone Events by the applicable deadline:
Actual (A)/Projected (P) Completion Date
1. Commence Production of pile installation
February 11, 2013
February 13, 2013 (A)
2. Commence factory tenant improvements
March 4, 2013
April 8, 2013 (A)
3. Commence onsite steel erection
June 17, 2013
August 15, 2013 (A)
4. Commence factory module production
July 8, 2013
July 31, 2013 (A)
5. Begin module erection onsite
August 19, 2013
December 12, 2013 (A)
6. Onsite module erection complete
April 18, 2014
June 15, 2015 (P)
7. Elevator machine room acceptance by elevator Subcontractor
May 19, 2014
September 2, 2015 (P)
8. Onsite mateline work complete
June 9, 2014
June 29, 2015 (P)
9. Substantial Completion
July 25, 2014
September 9, 2015 (P)